Step 1: Make the
F-1010E Tie Down Bar from the length of AEX TIE DOWN X
7.5000 provided in the kit. Trim to size, then tap shown
in Figure 1.
|
|
Step 2: Remove
the vinyl from the F-1012 A & B Fuselage Bulkheads,
Deburr, then cleco them together as shown in Figure 2.
However, Don't install any clecos in the holes that are associated
with the F-1012 E Tie Down Bars.
|
|
Step 3: Draw
Lines along the top and side of the aft face of the F-1012
e Tie Down Bar using the Dimensions in Figure 2.
Center these lines in the appropriate holes in the
F-1012 A & B Fuselage Bulkheads then clamp the tie
down bar into position.

Match-Drill the four 3/32" holes of the bulkheads into the
tie down bar with a #30 drill, cleco these holes. |
|
Then
match-drill the 3/16" holes with a 3/16"drill. |
|
Step 4: Make
the F-1011E Rudder Cable Angle, as shown in Figure 3, from
the length of AA6-063 x 3/4 x 3/4 provided in the kit.
|
|
Sep 5: Match drill the nut plate rivet holes into the F-1011E Rudder
Cable Angle as shown in Figure 4. The nut plates can be
temporarily held in place with AN-3 bolts while the holes
are drilled. Match-Drill one rivet hole and cleco it
before drilling the second. This will prevent the nut plate
from rotating before the second hole is match-drilled.
Machine Countersink the rivet holes in the rudder
cable angle for 3/32" flush rivets. DO not rivet the nut plates
into place yet. |
|
Step 6: Cut the
F-1011A Bulkhead Stiffener, using the dimension shown in Figure
5, from one of the six foot lengths of J-channel provided
in the kit. Deburr the edges.
|
|
| Page 10-3 |
Note: The two F-1011 C Horizontal Stabilizer
Attachment Bars are most likely bowed die to the punching
operation used during their manufacture. This bow will
have to be removed.
Step 1: Place one of the
F-1011C Horizontal Stabilizer Bars in a padded vice near
one of the ends. Pre load the free end of the attachment
bar in the direction required to straighten it and, using
a rubber mallet, firmly strike the bar one time near the
vice. Slide the bar further into the vice, pre load and
strike the bar again. Repeat this until the bar is
straight within a 1/16" along its entire length. |
|
Step 2: Finish the
edges of the two F-1011 C Horizontal Stabilizer Attachment
bars, then cleco them to the front of the F-1011 Bulkhead
as shown in Figure 2.Except for the bottom hole in each
attachment bar (The hole shared with the F-1011A
Stiffener), final drill the holes in common to the
attachment bar and bulkhead using a #30 Drill. |
|
Step 3: Place the F-1011A
Bulkhead Stiffener on the back of the F-1011 Bulkhead as
shown in Figure 2. Center the stiffener between the sides
of the bulkhead with the top of the stiffener flange a
quarter inch above the holes in the bulkheads depicted in Figure
3
Clamp the stiffener in place, then match drill the
holes of the bulkhead (and the bottom holes in the F-1011C
Attachment bars) into the stiffener with a #30 drill.
Install clecos while drilling.
|
Step 4: Drill the two
1/8" holes indicated in Figure 3 to 5/8" using a
unibit step drill |
|
Step 5: Repeat
Step 3 for locating and drilling the four holes used to
attach the F-1011E Rudder Cable Angle. The top of the
rudder cable angle is located 7/16" above the holes
in the F-1011 Bulkhead as shown in Figure 3. |
|
|
|
|